    Ready Mix Concrete Truck Calculator

    This concrete calculator for ready mix turns a volume into truck loads. Enter cubic yards, cubic meters, or slab dimensions, then set the truck capacity (default 10 yd³). The tool divides the volume by the capacity and rounds up to whole trucks, showing the size of the last load and a 10% waste allowance.

    Published How we calculate

    Ready-mix truck calculator

    Calculate by

    Ask your supplier for the capacity of its trucks.

    Live diagram
    14 yd³1 m³ (1.31 yd³)

    Your estimate

    Total volume with waste

    15.40yd³

    Cubic meters
    11.77 m³
    Cubic feet
    415.8 ft³

    Premixed bags

    • 80 lb bags693
    • 60 lb bags924
    • 40 lb bags1,386
    • 25 kg bags1,013
    • 20 kg bags1,260
    Weight
    62,298 lb · 28,258 kg
    Ready-mix truck loads (10 yd³ each)
    1.54

    Trucks needed (rounded up)

    2

    Formula with your numbers

    378 ft³ × 1.1 = 415.80 ft³

    Includes a 10% waste allowance. Bags are rounded up. Weight uses 2,400 kg/m³ (150 lb/ft³).

    Planning several pours or a cost sheet? Get the free Excel template (7 tabs, no sign-up).

    How to Use the Ready Mixed Concrete Calculator

    To use the ready-mix calculator, follow these 4 steps.

    1. Enter the volume, or pick Dimensions and measure the pour.
    2. Set the truck capacity your supplier gives you, in cubic yards or cubic meters.
    3. Keep 5 to 10 percent for waste; the default is 10 percent.
    4. Read the truck count and the size of the last load.

    Concrete Calculator Ready Mix Formula

    The ready-mix formula divides volume ÷ truck capacity and rounds the answer up to a whole truck.

    Trucks = volume (yd³) ÷ truck capacity (yd³), rounded up

    Last load = volume − (trucks − 1) × capacity

    • Volume: the concrete to order in cubic yards (yd³), waste included.
    • Truck capacity: the load one concrete mixer truck carries, 10 yd³ by default.
    • Last load: the part load on the final truck.

    The metric formula uses cubic meters (m³) for the volume and the truck. Ten cubic yards equal 7.65 m³.

    Trucks = volume (m³) ÷ truck capacity (m³), rounded up

    1 yd³ = 0.7646 m³

    Worked Example: 14 Cubic Yards in 10 Yard Trucks

    An order of 14 cubic yards (10.70 m³) needs 2 trucks: one full 10 yd³ load and one load of 4 yd³. The 3 steps below show the math.

    1. Divide by the capacity: 14 ÷ 10 = 1.4.
    2. Round up to whole trucks: 2 trucks.
    3. Find the last load: 14 − 1 × 10 = 4 yd³. With 10% waste, the order is 15.4 yd³, still 2 trucks.

    Where to Use the Truck Calculator

    The truck calculator helps plan 4 typical pours. Each example is 4 inches thick unless noted:

    • Garage floors: a 24 × 24 ft floor holds 7.11 yd³, or 1 truck with waste.
    • Driveways: a 50 × 16 ft drive at 5 in holds 12.35 yd³, or 2 trucks with waste.
    • Basement floors: a 30 × 40 ft floor holds 14.81 yd³, or 2 trucks with waste.
    • Small slabs: a 6 × 6 ft pad holds 0.44 yd³, or 22 bags of 80 lb concrete.

    What to Tell the Supplier

    To order concrete, give the supplier 3 details: the volume, the strength, and the slump.

    • Volume: the cubic yards from the calculator, such as 15.4 yd³ for the example.
    • Strength: about 3,000 pounds per square inch (psi), or 20 MPa, for patios and paths; about 4,000 psi (28 MPa) for driveways.
    • Slump: the measure of workability the supplier asks for. Ask which slump suits the job.

    Short-Load Fees

    A short-load fee is a charge some suppliers add when a truck carries less than their minimum load. Ask about the fee before you order, since a small last load can trigger it. Enter quoted fees in the cost calculator.

    Ready-Mix Trucks by Order Size

    A 10 yd³ truck carries 7.65 m³. The table shows trucks and the last load for common orders.

    Trucks needed at 10 yd³ per truck, volume as ordered
    OrderCubic metersTrucksLast load
    4 yd³3.0614 yd³
    8 yd³6.1218 yd³
    12 yd³9.1722 yd³
    14 yd³10.7024 yd³
    18 yd³13.7628 yd³
    25 yd³19.1135 yd³
    30 yd³22.94310 yd³
    42 yd³32.1152 yd³
    Change the truck capacity in the calculator to match your supplier.

    Common Ready-Mix Ordering Mistakes

    The 4 most common ordering mistakes are listed below.

    • Add waste before you count trucks. The extra 10 percent can push an order onto one more truck.
    • Confirm the truck capacity with the supplier. Every fleet differs.
    • Use bags for pours under about 1 cubic yard. One yard takes 45 bags of 80 lb concrete.
    • State the strength and slump on the order, not only the volume.

    Ready Mix Concrete Truck Calculator FAQ

    How many concrete trucks do I need for 14 yards?

    An order of 14 cubic yards needs 2 trucks at 10 yd³ each. The first truck carries a full 10 yd³ and the second carries 4 yd³. With 10 percent waste added, the order grows to 15.4 yd³ and still fits on 2 trucks.

    How much concrete does a truck carry?

    The calculator assumes 10 cubic yards (7.65 m³) per truck, a common full load. Truck sizes vary by supplier, so ask for the capacity of the trucks in the fleet. Type that number into the truck capacity box above to update the count.

    When are bags better than ready-mix concrete?

    Bags are better for pours under about 1 cubic yard, such as post holes, small pads, and repairs. One cubic yard takes 45 bags of 80 lb concrete. Above that size, the bag count passes 45, and a ready-mix truck delivers the whole pour at once.

    Does a concrete lorry hold the same as a truck?

    Yes, a concrete lorry is the UK name for a concrete mixer truck. UK suppliers quote loads in cubic meters, so switch the truck capacity unit to m³ and enter the load size from the supplier. The calculator divides the volume by that capacity and rounds up the same way.

    Sources

    Every result on this page uses plain geometry and the exact unit definitions below. The full list of formulas and constants is on the How we calculate page.

    1. NIST – Unit conversion: SI to U.S. customary units
    2. How we calculate – formulas, constants, and sources